data load taking long time

2 posts in Backup and Recovery Last posting was on 2001-03-09 02:01:49.0Z
jbuhl Posted on 2001-03-09 01:50:31.0Z
From: "jbuhl" <jbuhl@peerdigital>
Subject: data load taking long time
Date: Thu, 8 Mar 2001 18:50:31 -0700
Lines: 16
X-Priority: 3
X-MSMail-Priority: Normal
X-Newsreader: Microsoft Outlook Express 5.00.2919.6600
X-MimeOLE: Produced By Microsoft MimeOLE V5.00.2919.6600
Message-ID: <5z4Xd3DqAHA.253@forums.sybase.com>
Newsgroups: sybase.public.sqlserver.backup+recovery
NNTP-Posting-Host: 12.41.162.201
Path: forums-1-dub!forums-master.sybase.com!forums.sybase.com
Xref: forums-1-dub sybase.public.sqlserver.backup+recovery:438
Article PK: 1060986

Hello,


We just got a requirement to benchmark our database to a size of 20GB. The
production db is on about 2GB. I make a 20 GB database on another server
and load the 2 GB database into it. It takes about the same time to load
but at the end the backupserver give a message of "load complete" but then
hangs out for about 20 minutes before it finaly lets go. The dataserver
process is churning 48% of 1 of 2 cpu's. Thats about the only thing running
on the box as well.

any idea's

Joe Buhl


Anthony Mandic <amandic Posted on 2001-03-09 02:01:49.0Z
Date: Fri, 09 Mar 2001 13:01:49 +1100
From: Anthony Mandic <amandic@*t.com.au>
Organization: Mandic Consulting Pty. Ltd.
X-Mailer: Mozilla 4.72 [en] (X11; U; Linux 2.2.14-5.0 i686)
X-Accept-Language: en
MIME-Version: 1.0
Subject: Re: data load taking long time
References: <5z4Xd3DqAHA.253@forums.sybase.com>
Content-Type: text/plain; charset=iso-8859-1
Content-Transfer-Encoding: 8bit
Message-ID: <aNvvz8DqAHA.301@forums.sybase.com>
Newsgroups: sybase.public.sqlserver.backup+recovery
Lines: 15
NNTP-Posting-Host: 210.9.51.46
Path: forums-1-dub!forums-master.sybase.com!forums.sybase.com
Xref: forums-1-dub sybase.public.sqlserver.backup+recovery:437
Article PK: 1060985


jbuhl wrote:

> We just got a requirement to benchmark our database to a size of 20GB. The
> production db is on about 2GB. I make a 20 GB database on another server
> and load the 2 GB database into it. It takes about the same time to load
> but at the end the backupserver give a message of "load complete" but then
> hangs out for about 20 minutes before it finaly lets go. The dataserver
> process is churning 48% of 1 of 2 cpu's. Thats about the only thing running
> on the box as well.

It clearing pages not loaded or not in the original dump file.

-am © 2001